Run a fruit pulper FAT with a fixed test basis, three-stream mass balance and signed acceptance record.

A factory acceptance test is useful only when the buyer and supplier record the same feed, settings, sampling window and acceptance limits. This checklist structures that record without inventing a universal test duration, capacity, yield or screen setting.

Watermarked factory-test reference derivative showing tomato pulp leaving a pulper outlet
Approved factory-test run reference derivative showing a temporary output check; it is not formal FAT, acceptance proof or a yield claim.
01

Freeze the test basis before feeding product

Identify the fruit lot, variety, maturity, preparation, temperature range, target product and reject limits. Record whether the quoted rate means prepared feed or finished output, and list every upstream or downstream interface used during the test.

02

Define and observe a stable run window

Agree how stable operation will be recognized, then record start and finish times, feed interruptions, adjustments and abnormal events. Results taken while settings or feed conditions are changing must be labelled rather than blended into the accepted window.

03

Close the evidence and action record

Reconcile prepared feed, accepted product and reject with flush water, recirculation and retained material. Link samples to times and settings, complete the cleaning and reassembly checks, then record accepted items, open actions, owners and signatures.

Minimum fruit pulper FAT evidence pack
Evidence groupRecord togetherDecision protected
Test basisLot, preparation, temperature, target product and agreed rate basisPrevents a different feed or capacity definition being accepted
Machine stateScreen identity, speed, clearance, reject restriction and every adjustmentConnects results to a reproducible configuration
Three streamsPrepared feed, accepted product, reject and balance adjustmentsPrevents a one-sided yield or quality conclusion
CloseoutSamples, cleaning, reassembly, deviations, actions and signaturesSeparates passed evidence from unresolved work

Calculate a measured trial

Use kilograms on one collection basis, record quality observations separately and export a record.

Open trial planner

Questions before a trial

How long should the stable run last?

There is no universal duration. Agree a window long enough to observe stable feed, settings and outlet sampling for the project, and record interruptions or transitions separately.

Does a balanced mass prove product quality?

No. The balance checks accounting around the three streams; linked product and reject samples must still meet the agreed quality observations or measurements.

Can the FAT close before cleaning and reassembly?

Only if the approved scope explicitly excludes those activities. When cleanability or changeover is part of acceptance, the test remains open until inspection, reassembly and outstanding actions are recorded.

Technical references and scope

These sources explain general mechanisms and methods. Another supplier's model, rating or claimed results are not specifications for fruitpulper.com.

Equipment quotation

Tell us what the machine will process.

Send the fruit, prepared-feed rate and target pulp or puree. Include a drawing or trial record when available; you can enquire without a screen size.