A factory acceptance test is useful only when the buyer and supplier record the same feed, settings, sampling window and acceptance limits. This checklist structures that record without inventing a universal test duration, capacity, yield or screen setting.

Freeze the test basis before feeding product
Identify the fruit lot, variety, maturity, preparation, temperature range, target product and reject limits. Record whether the quoted rate means prepared feed or finished output, and list every upstream or downstream interface used during the test.
Define and observe a stable run window
Agree how stable operation will be recognized, then record start and finish times, feed interruptions, adjustments and abnormal events. Results taken while settings or feed conditions are changing must be labelled rather than blended into the accepted window.
Close the evidence and action record
Reconcile prepared feed, accepted product and reject with flush water, recirculation and retained material. Link samples to times and settings, complete the cleaning and reassembly checks, then record accepted items, open actions, owners and signatures.
| Evidence group | Record together | Decision protected |
|---|---|---|
| Test basis | Lot, preparation, temperature, target product and agreed rate basis | Prevents a different feed or capacity definition being accepted |
| Machine state | Screen identity, speed, clearance, reject restriction and every adjustment | Connects results to a reproducible configuration |
| Three streams | Prepared feed, accepted product, reject and balance adjustments | Prevents a one-sided yield or quality conclusion |
| Closeout | Samples, cleaning, reassembly, deviations, actions and signatures | Separates passed evidence from unresolved work |
Keep a common record
Printable fruit pulper FAT record
Complete each item with a value, document reference, pass/fail result or an explicit not-applicable reason. Blank fields are unresolved evidence.
Test lot and agreed basis
| Item to agree or record | Value / evidence / decision |
|---|---|
| Project, quotation, machine and test-record identifiers | Write on the printed copy |
| Test date, location, buyer witnesses and supplier witnesses | Write on the printed copy |
| Fruit or vegetable, variety, maturity, size range and lot reference | Write on the printed copy |
| Feed temperature and preparation steps before the pulper | Write on the printed copy |
| Target product, unwanted-solids limits and sampling method | Write on the printed copy |
| Prepared-feed rate basis, operating window and allowed deviations | Write on the printed copy |
Stable run and machine settings
| Item to agree or record | Value / evidence / decision |
|---|---|
| Stable-run start, finish and agreed stability rule | Write on the printed copy |
| Screen identifier, aperture, pattern, thickness and open area when documented | Write on the printed copy |
| Rotor, paddle or screw configuration and direction | Write on the printed copy |
| Recorded speed, paddle-screen clearance and reject restriction | Write on the printed copy |
| Feed-control method and upstream/downstream interface state | Write on the printed copy |
| Every adjustment, interruption, blockage, vibration or abnormal event with time | Write on the printed copy |
Three-stream mass balance
| Item to agree or record | Value / evidence / decision |
|---|---|
| Prepared feed measured during the stable run | Write on the printed copy |
| Accepted product measured during the same window | Write on the printed copy |
| Reject stream measured during the same window | Write on the printed copy |
| Flush water, recirculation, spills and retained material recorded separately | Write on the printed copy |
| Measurement devices, units, resolution and tare method recorded | Write on the printed copy |
| Calculated balance difference reviewed and explained before acceptance | Write on the printed copy |
Sampling and acceptance
| Item to agree or record | Value / evidence / decision |
|---|---|
| Feed, accepted-product and reject sample IDs linked to time and settings | Write on the printed copy |
| Product texture, visible peel, seed, fibre or fragment observations | Write on the printed copy |
| Reject composition, useful product retention and stone integrity where relevant | Write on the printed copy |
| Screen loading or blinding observations and sample photographs where approved | Write on the printed copy |
| Each agreed acceptance criterion marked pass, fail, conditional or not applicable | Write on the printed copy |
| Deviations and repeat-test requirements assigned an owner and due date | Write on the printed copy |
Cleaning, reassembly and sign-off
| Item to agree or record | Value / evidence / decision |
|---|---|
| Supplier safe-shutdown and isolation procedure followed before opening | Write on the printed copy |
| Screen, rotor and product-contact access sequence recorded with tools or lifting needs | Write on the printed copy |
| Drain-down, trapped-product points and post-clean inspection recorded | Write on the printed copy |
| Removed parts reassembled and guards or interlocks checked under the approved procedure | Write on the printed copy |
| Open actions, document attachments and conditional acceptance stated | Write on the printed copy |
| Buyer and supplier names, roles, signatures and dates recorded | Write on the printed copy |
Questions before a trial
How long should the stable run last?
There is no universal duration. Agree a window long enough to observe stable feed, settings and outlet sampling for the project, and record interruptions or transitions separately.
Does a balanced mass prove product quality?
No. The balance checks accounting around the three streams; linked product and reject samples must still meet the agreed quality observations or measurements.
Can the FAT close before cleaning and reassembly?
Only if the approved scope explicitly excludes those activities. When cleanability or changeover is part of acceptance, the test remains open until inspection, reassembly and outstanding actions are recorded.
Technical references and scope
These sources explain general mechanisms and methods. Another supplier's model, rating or claimed results are not specifications for fruitpulper.com.
Equipment quotation
Tell us what the machine will process.
Send the fruit, prepared-feed rate and target pulp or puree. Include a drawing or trial record when available; you can enquire without a screen size.